Scheduling of the Tasks
2009
- Surface investigation work in the region of BAF for the construction of an URL ; Phase I: carrying on the site qualification test program
2010
- Surface investigation work in the region of BAF for the construction of an URL; Phase I: carrying on the site qualification test program
2011
- Surface investigation work in the region of BAF for the construction of an URL; Phase I: completion of the site qualification test program, the final selection of the site for the URL. Preparation of the underground investigation report within the site qualification test program and obtaining the regulatory approval thereto.
2012-2019
- Surface investigation work in the region of BAF for the construction of URL; Phase II:
- Development of the investigation plan for the URL
- Start of construction of the URL
2013
- Return shipment of the spent fuels from KFKI – Central Research Institute for Physics (and possibly from BUTE – Budapest University of Technology and Economy) to Russia
2020–2046
- Completion of construction of the laboratory
- Implementation of the investigation program and preparation for the investment
- Construction of the HLW repository
2027-2028
- Return shipment of the spent fuels of KFKI (and possibly BUTE) to Russia
2047–2069
- Phase 1 operation of the HLW repository
- Transfer of spent fuels stored in the ISFS to the new facility
2047
- Transfer of radioactive wastes stored at Püspökszilágy to the new facility
2070–2094
- Operation of the HLW repository and waiting for the transfer of decommissioning wastes
2093–2094
- Extension of the capacity of the HLW repository to allow the receipt of decommissioning wastes
2095–2104
- Phase 2 operation of the HLW repository
- Transfer of wastes arising from the dismantling Paks Nuclear Power Plant and loading into the repository facility
2105–2108
- Closure/sealing of the HLW repository
- Environment monitoring